EMBRAER PRESENT AT THE 3 KOREAN AEROSPACE AND DEFENSE EXHIBITION

Published

October 15, 2001

Share

EMBRAER PRESENT AT THE 3 KOREAN AEROSPACE AND DEFENSE EXHIBITION

Seoul, October 15, 2001 – Embraer is firm with its plans to become ever more present in the Asian commercial aviation market. In a well laid-out stand at the Korean Aerospace & Defense Exhibition 2001, visitors will have the opportunity to have a broader view of the wide range of products made by Embraer, including information on its newest aircraft, the ERJ 170/190.

Embraer has been looking dearly at the Asian commercial aviation market since the 50-seat ERJ 145 entered revenue service in 1996. Its characteristics of passenger comfort, performance and low operational costs were envisaged as the right answer to Asian operators’ expansion plans.

“In our first participation at the Seoul exhibition we want to stress that Embraer regards Asia in general and Korea in particular as truly important markets where our aircraft fit to perfection, be the ERJ 135/140/145 regional jet family, be the new ERJ 170/190 family of jetliners of up to 108 seats”, said Luiz Fuchs, Director Marketing & Sales Asia & Pacific for Embraer.

The first sell to Asia comprised five ERJ 145s to Sichuan Airlines and first delivery – serial number 317 with B3040 register – occurred about one year ago, on Sept. 21, amid a beautiful ceremony held at the Embraer headquarters and main plant in São José dos Campos.

Embraer’s commitment to Asia has lead to the opening of representative offices as to provide full support to operators in the region. In May of 2000, the Beijing, China office was inaugurated. A second representative office in the region, in Singapore, was set later in the year, in December.

Although not exactly in Asia, Embraer had inaugurated in May of 1998 the Melbourne office in Australia, not only dedicated to sales and customer support but also to spare parts distribution to Australia and Polynesia. These three representative offices signify a wide Embraer customer base service in this side of the world.

In another clear demonstration of its commitment to Asia, Embraer announced last June, during the 44th Paris Air Show, the establishing of an aircraft spare parts center in Beijing, as to assure successful operations of its products in the Chinese and other markets.

The Spare Parts Center, jointly established by Embraer and the China Aviation Supplies Import and Export Corporation, will ensure the total guarantee of effective and adequate customer support to Chinese and other Asian and Australian operators. Embraer is also involved with Asian suppliers, such as Kawasaki Heavy Industries of Japan, the supplier important parts such as wings for the new jetliner family.

One of the more significant achievements for Embraer is bound to happen shortly: the new 70-seater ERJ 170 will roll out on upcoming October 29th, just 28 months after the program go-ahead in June of 1999 during the Paris Air Show of that year.

The development of the new Embraer jetliner was rather complex and largely based upon the Advisory Boards that involved customers, both actual and potential. Their opinions and suggestions following aircraft presentations were truly valuable and entailed steering for its final project in a way to become a full customer-driven aircraft.

The Advisory Boards, together with Steering Groups and Man-Machine Interface meetings, totaled four in 1999 – two of them actually before the program go-ahead –, three in 2000 and five in 2001.

To accomplish the roll-out on the scheduled date, all phases of designing, planning and first prototype construction were strictly adhered to schedule. A brief review of the entire process tells more.

In Sept. 28th, 2000 the ERJ 170 reached what is called the critical design review (CDR) stage. Despite the challenging schedule to design and develop an entirely new aircraft, several milestones were reached during the second and third quarters of 2000, each one occurring according to a schedule established when Program ERJ 170/190 was launched.

Performed between Embraer and its risk-sharing partners and suppliers, the first CDR meetings were held on that September. Aimed exclusively at verifying the engineering solutions chosen for each area of the airframe and systems, the CDRs performed the important role of determining the engineering full compliance with the project’s targets and requirements. Besides the CDRs with partners, Program ERJ 170/190 launch customer, Switzerland-based Crossair has also done critical design reviews with Embraer.

Since the International Civil Aviation Organization (ICAO) had launched and refined the CNS/ATM (Communications-Navigation-Surveillance/Air Traffic Management) concept, Embraer has steadily accompanied its evolution. Composed by representatives from the Company, customers and suppliers, the CNS/ATM Planning Team at the plant had been formed a year before, in June of 1999, as to assess the many requirements that the concept engenders and its impact on existing and future Company products.

In March 30, 2001 Embraer announced another ERJ 170/190 program milestone: the coming of the first wing stub from Kawasaki. The component was freighted to Brazil after approval by Japan’s airworthiness certification authority (JCAB) in coordination with Brazilian authorities (CTA).

The wing stub was to arrive at Embraer’s headquarters early April, as it eventually did. Serving as an attachment point for the aircraft’s wings, the box-shaped wing stub is a key structural component of the ERJ 170/190 jetliners. After inspection, it was ventrally fitted to center fuselage II, thus registering the first major, mating event of an assembly supplied by a risk-sharing partner.

Over the following weeks, additional parts and components were to arrive at Embraer, some coming from suppliers Latecoère (France) and Sonaca (Belgium). Final assembly of the first ERJ 170 was ready to start in June.

Before that, in May 8th, 2001 Embraer began the Joint Definition Phase (JDP) of the ERJ 190, a major milestone program made possible three months earlier than planned due to smooth-running ERJ 170 program.

The start of the ERJ 190 JDP followed closely on the steps of Kawasaki, assigned to manufacture the ERJ 190’s wings. This choice enhanced the high degree of commonality between the ERJ 170 and ERJ 190, as all partners are the same in both programs.

In June 18, 2001 during the 44th Paris Air Show, Embraer announced the start of ERJ 170 prototype no. 1 assembly. Following installation of the wing stub to the center fuselage section II, work concentrated on mating this major assembly item to the center fuselage I and center fuselage III sections, and rear fuselage. Fuselage work was to be completed in early July.

Parallel to those tasks, Embraer completed the assembly of the first set of ERJ 170 wings by the end of the month, to be mated to the fuselage shortly after, in early August. That month also marked the beginning of the last phase of final assembly work. During the next three months the prototype would be fitted with all its systems, as well as receiving the last major sub-assemblies.

Another major accomplishment was the completion of the wings assembly late June, which was integrated by Embraer with parts supplied by Kawasaki and Sonaca and other sub-contractors around the world. The mating of the wing to the fuselage was to take place within the next couple of weeks.

In July 26, 2001 Embraer completed the mating of the ERJ 170 fuselage, ten days ahead of schedule. The fuselage is composed of the Embraer forward fuselage, the Embraer/ Sonaca (Belgium)/ Kawasaki (Japan) center fuselage II, the Latecoère (France) center fuselage I and III and the Gamesa (Spain) rear fuselage section.

Notwithstanding the challenges of the fast-paced development program, that critical ERJ 170 milestone was performed flawlessly. The interfaces between major sections designed and produced by the partners in different countries exceeded the expectations of quality and tolerances and allowed the assembly to be performed in much less time than forecasted.

This event further underscored the great integration between Embraer and the many risk-sharing partners that are participating in the development and manufacture of this new family of jetliners.

In August 13, 2001 the wings of the aircraft were eventually fitted to the fuselage. This event marked the conclusion of another step in the final assembly of the ERJ 170 prototype, which was progressing faster than originally planned.

While the different fuselage sections were mated during the last half of July, final work was made for fitting-out the wings by installing the required systems on them. Embraer and Kawasaki carried out wings assembly, with the Japanese risk-partner supplying the leading and trailing structures, spars and surfaces. Sonaca supplied slats and Embraer, skins and ribs. Once these two major assemblies were finished, the following step was to mate the wings with the fuselage.

Smoothly performed by Embraer technicians and with an exceptional low level of snags which demonstrated the correct application of advanced technology in design and manufacturing, including all the latest CAD, CAE, digital mock-up, virtual reality, and digital manufacturing tools, all of these assembly milestones were executed with production tooling and jigs. This further ensures that once ERJ 170 production begins it will be completely trouble-free.

After accomplishing these tasks at the scheduled time, Embraer engineers and technicians concentrated their efforts to equipping the ERJ 170 first prototype with all of its systems, as well as to receive the last major sub-assemblies. This brought the first ERJ 170 closer to the roll out and the maiden flight shortly after, all within the schedule outlined a little over two years ago.

In September 21, 2001 work on the ERJ 170 proceeded at full steam at the new assembly hangar. The vertical empennage was fitted to aircraft number 1, thus enabling a better visualization of ERJ 170’s proportions. The tail section, wing flaps, ailerons and landing gear have been fitted to the aircraft. The horizontal plan and the tail cone were already in site and their junction to fuselage would follow soon. The ERJ 170 took shape after barely 27 months after the program go-ahead, a clear demonstration of precise planning and deep commitment of Embraer to produce the new jetliner.

In October 8th , 2001 engine pylons were fitted to the wings, and within a week approximately the two General Electric CF34-8E engines with nacelles will be fit into place. The landing gear has also been installed.

What can be seen now for those entering Building F-220 at the São José dos Campos is the full, real shape of Embraer’s new bird, the 70-seat ERJ 170 which, along with larger sister ERJ 190 shall reinforce the Company’s presence in the world markets well into the 21st century.}}